Free Resource No sign-up required

The PMP® Formula Sheet 2026 Edition

Every formula that can appear on the 2026 PMP exam — explained in plain English, with a worked example for each. Fifteen formulas. One evening. Free points.

Reviewed by a PMBOK® Guide 8th Edition contributor Updated July 2026 · aligned to the current ECO 15 formulas · worked examples · linked deep-dives

A quick word from our instructors: the 2026 exam has fewer pure-calculation questions than the old exams did — but the ones that appear are free points if you know these cold, and the concepts behind them (what a CPI of 0.83 actually tells a project manager) show up constantly in situational questions.

Earned Value — the core four

The four numbers every other formula is built from.

Planned Value

PV = Planned % Complete × BAC

What the schedule says you should have earned by today.

Example: Budget $100k, 40% planned by today → PV = $40,000.

Full definition & exam guide

Earned Value

EV = Actual % Complete × BAC

What the completed work is actually worth — the anchor of every other formula.

Example: 35% genuinely done on a $100k budget → EV = $35,000.

Full definition & exam guide

Cost Variance

CV = EV − AC

Negative = over budget. EV always comes first.

Example: EV 35k, AC 42k → CV = −$7,000: over budget.

Full definition & exam guide

Schedule Variance

SV = EV − PV

Negative = behind schedule.

Example: EV 35k, PV 40k → SV = −$5,000: behind.

Full definition & exam guide

Performance indexes

Ratios the exam loves — and the numbers real steering committees read first.

Cost Performance Index

CPI = EV ÷ AC

Value earned per dollar spent. Below 1.0 = over budget.

Example: 35k ÷ 42k = 0.83 → getting 83¢ of work per $1.

Full definition & exam guide

Schedule Performance Index

SPI = EV ÷ PV

Work rate vs. plan. Below 1.0 = behind schedule.

Example: 35k ÷ 40k = 0.875 → moving at 87.5% of planned pace.

Full definition & exam guide

Forecasting

Where the exam tests judgment: choosing the right formula for the scenario.

Estimate at Completion (typical)

EAC = BAC ÷ CPI

Final cost if current efficiency continues — the default EAC on the exam.

Example: 100k ÷ 0.83 ≈ $120,500 forecast at completion.

Full definition & exam guide

Estimate at Completion (one-time blip)

EAC = AC + (BAC − EV)

Use when the overrun was a one-off and the rest will go to plan.

Example: 42k + (100k − 35k) = $107,000.

Full definition & exam guide

Estimate to Complete

ETC = EAC − AC

Money still needed from today — the number sponsors actually ask for.

Example: 120.5k − 42k = $78,500 to finish.

Full definition & exam guide

Variance at Completion

VAC = BAC − EAC

Size of the final surprise. Negative = overrun coming.

Example: 100k − 120.5k = −$20,500.

Full definition & exam guide

To-Complete Performance Index

TCPI = (BAC − EV) ÷ (BAC − AC)

Efficiency required on remaining work to hit budget. Above ~1.10 = unrealistic; re-baseline.

Example: 65k ÷ 58k = 1.12 → a turnaround promise.

Full definition & exam guide

Schedule & estimating

The classics that still earn quick points.

Total Float

Float = LS − ES (or LF − EF)

How long a task can slip without moving the finish date. Critical path float = 0.

Example: ES day 3, LS day 6 → 3 days of float.

Full definition & exam guide

PERT (Beta) Estimate

E = (O + 4M + P) ÷ 6

Weighted three-point estimate — optimistic, most likely ×4, pessimistic.

Example: (4 + 4×6 + 14) ÷ 6 = 7 days.

PERT Standard Deviation

σ = (P − O) ÷ 6

The uncertainty range around a PERT estimate.

Example: (14 − 4) ÷ 6 ≈ 1.67 days.

Communication Channels

Channels = n(n−1) ÷ 2

Why adding people multiplies communication complexity.

Example: 10 people → 45 channels. Add 2 more → 66.

Formulas memorized? Now train the judgment.

The 2026 exam gives you 180 questions in 240 minutes — and most of them test decisions, not arithmetic. Put these formulas to work inside realistic situational questions, free to start.

Sharing this sheet with your study group, class, or blog? Link to this page — it stays updated as PMI updates the exam. Written and maintained by the PMLearning instructor team.